For repairs of all kinds, HEINRICH HARBISCH has two stern docks at its disposal:
- Dock1, 30 m long, with an external / internal width of 20 m / 16.5 m
- Dock2, 26 m long, with an external / internal width of 14 m / 11.5 m
These allow us to lift either the bow or stern out of the water, for example to change propellers, repair shafts and rudders or carry out welding work.
Both docks were designed, developed and completed by us, although we too rely on dependable partners: engineers were involved in planning both docks. Construction of
- Dock1 initially took place at NRSW Neue Ruhrorter Schiffswerft GmbH in Duisburg and was completed at our own premises; commissioned in November 2011
- Dock2 was built by our own employees on rented open ground near our shipyard, alongside normal shipyard operations; commissioned in November 1991.